Lockout Tagout Steps Before Machine Repair: Isolate First

Follow lockout tagout steps before machine repair: stop, isolate, lock and tag every energy source, release stored energy, and prove zero energy first.

Red padlock on an open disconnect box beside a stopped conveyor motor, with a voltage tester and gloves on a steel tool tray.

Lockout tagout steps before machine repair: isolate first, then diagnose

Lockout tagout steps before machine repair come first, every time. Stop the machine, isolate every energy source, apply your personal lock and tag at each isolation point, release stored energy, and prove zero energy with a tester before you touch anything. Only then start diagnosing. Any check that needs power on must follow your site's written procedure and be done by a qualified person.

Why Isolation Comes Before Diagnosis

A motor hums but won't turn. The temptation is obvious: put a meter on the terminals, press the start button, and watch what happens. That habit is how people get hurt. A motor that hums and stalls is often fighting a mechanical jam, an open phase, or a seized load. The moment it is energized, rotating parts, stored energy, and unexpected movement are all in play, and the person closest to the machine is the one most exposed.

Checks That Need the Machine Energized

Some checks genuinely need power, such as measuring voltage at a drive input under load or reading a drive display while it runs. These are not casual checks. They belong to a controlled procedure, with the hazards explained first, the energy control steps set up for that exact job, and a qualified person doing the work.

What a Live Check Can and Cannot Tell You

A live check shows one moment on one circuit. It cannot tell you whether the lock is on the right disconnect, whether a hydraulic line still holds pressure, or whether someone is inside a guard. Most diagnosis of a dead-looking fault can be done de-energized: checking continuity, insulation, mechanical free movement, fluid levels, fuse and breaker state, and sensor wiring. Start there.

The Lockout Tagout Sequence, Step by Step

Your site's written energy control procedure is the authority. The order below is the general sequence most procedures follow.

  1. Tell people. Notify operators and anyone working nearby that the machine is going down and why.
  2. Shut down normally. Use the machine's own stop control so the process ends in a known state.
  3. Open every disconnect. Switch off each isolating device you identified.
  4. Lock and tag each point. Apply your personal lock and a tag at every isolation point.
  5. Release stored energy. Deal with pressure, springs, and loads (see the next section).
  6. Verify zero energy. Prove it before any hands-on work.

Find Every Energy Source Before You Switch Anything Off

Walk the machine and list every source: the main electrical feed, control circuits, a separate supply for a heater or brake, compressed air, hydraulic pressure, gravity loads, and any energy the procedure names. Write them on your job list. A machine often has more than one source, and the one you forget is the one that causes the injury.

Shut Down, Isolate, Lock, and Tag

Each person working on the machine applies their own lock to the isolation point, with their own key, and keeps it on until they finish. Where several people are involved, a multi-lock hasp lets everyone add a lock. Tags say who applied the lock, when, and why, but a tag is never a substitute for a lock. Never remove a lock that belongs to someone else.

Stored Energy and Proving the Machine Is Dead

Isolation removes the supply, not everything else. Hydraulic pressure stays in lines and accumulators after the pump stops. Springs stay loaded. A raised conveyor section, a hoist arm, or a suspended guard can drop. Drives with DC link capacitors can hold charge after power is removed.

  • Block suspended loads before you work under them.
  • Bleed hydraulic pressure using the method the procedure gives.
  • Secure or relax springs as specified.
  • Wait the time stated on the drive or equipment label before opening enclosures.

Then prove the machine is dead. Confirm zero energy before you touch anything. Use a meter or tester rated for the circuit voltage, test it on a known live source first, and then test the isolated circuit. Attempt a start from the local control only after you have confirmed it is safe and everyone is clear. Do not trust a switch position, a panel light, or a colleague's word on its own.

Where Diagnosis Fits After the Machine Is Locked Out

Once the machine is safe, diagnosis begins. Describing the fault in plain words helps you order the checks. "Motor hums, shaft won't turn" points toward mechanical binding, a phase loss, or a motor fault, and several of those checks can be done with power locked out: turning the shaft by hand, inspecting the coupling, checking the brake, and examining fuses and terminal tightness.

Using the Symptom to Plan Checks Without Re-energizing

Fault Line AI is a web app for maintenance technicians. You describe what the machine is doing in plain words, and it suggests the likely causes and the next check to run, one step at a time, with a reason next to each check. It has built-in checks for motor hum or no start, hydraulic pressure loss, drive overcurrent or trips, and overheating or shutdown, plus a general list for other faults. It does not connect to or control machines, and it does not include lockout tagout steps. You still follow your site's own energy control procedure.

For the check order in each family, read motor and drive fault troubleshooting, check by check and hydraulic pressure loss troubleshooting. For the first minutes after a stop, see what to check first when a machine goes down. For a broader look at the tool, see the troubleshooting tool for live faults.

Common Lockout Mistakes and Handover Problems

The same failures come up again and again:

  • Removing another person's lock because their work seems finished.
  • Restoring power when one person completes a task while others are still working.
  • Skipping verification because the fault looks minor.
  • Leaving a machine isolated at shift change with no written note.

At shift change, the incoming technician should walk the machine, confirm every lock and tag, read the handover note, and know exactly who still holds a lock. Record the machine, each isolation point, who holds which lock, what was checked, and what remains open. Before the machine returns to service, remove locks only in the order the procedure sets, and confirm everyone is clear.

Frequently Asked Questions

Does Fault Line AI include lockout tagout steps?

No. Fault Line AI suggests likely causes and the next check, with a reason for each one. It does not isolate, lock out, or control a machine. Your site's energy control procedure governs isolation.

Can I troubleshoot a machine while it is locked out?

Yes, for checks that can be done de-energized, such as inspecting couplings, fuses, and wiring. Checks that need power on belong to a controlled procedure carried out by a qualified person.

What should I do when a machine has more than one energy source?

List every source before shutdown, isolate each one at its own point, and apply a lock and tag at each. Verify zero energy at every circuit, not just at the main switch.

Once the machine is locked out and verified, try the guided troubleshooting in Fault Line AI. Describe the fault in plain words to get a ranked list of likely causes and the next check to run. You can use it without signing in, but its results are not saved, so write down the checks you run.